Hog Slat Inc. Newton Grove, NC USA February 2022 REV A11 8 Ventilation Systems 7. Cables should exit 90 Degrees to cabinet side to ensure even load on both sides of load block. Changing the exit angle will change force distribution on load block resulting in shorter load nut life. Figure 3 Figure 4 Figure 5 8. Install corner brackets, through wall brackets and hand winch. Use bearing supported pulleys on any pulley that rotates during operation of machine. Following figures show examples of external cabling and hand winch location. One machine used to pull two curtains from both sides, loop cable around pulleys. (Figure 3) One machine used to pull curtain from LEFT side, loop cable around pulleys. (Figure 4) One machine used to pull curtain from RIGHT side, loop cable around pulleys. (Figure 5)